SR-224 Underpass Project
Kimball Junction SR-224 Underpass Project
Your Underpass is DONE! We hope that you are able to come out and see and use this new trails amentity! We had a great ribbon cutting ceremony and now are looking forward to the completion of the trail from the Underpass to Bear Hollow, which should be done by Mid October.
This Underpass crossing connects the existing trails and sidewalk of Redstone east of Hwy 224 to the Millennium Trail on the west side of Hwy 224. ENJOY!
![]() |
Saturday, September 24th @ noon Ribbon Cutting Ceremony |
![]() |
Saturday, September 24th @ noon Ribbon Cutting Ceremony |
![]() |
Saturday, September 24th @ noon Ribbon Cutting Ceremony |
|
|
Saturday, September 17th Underpass COMPLETE! |
![]() |
Monday, August 29th |
![]() |
Thursday, August 25th @ 11:00am The concrete has been poured! |
![]() |
Tuesday, August 2nd @ 1:30pm Paving will be complete two lanes both directions, plus turn lane to UOP restored this afternoon. There will still be Underpass work on the shoulders for the next week or so, but traffic delays should be minimal. |
![]() |
Sunday, July 31st @ 11pm Crew continued placing pre-cast sections trying to make the Monday morning deadline to cross all four lanes |
![]() |
Sunday, July 31st |
![]() |
Sunday, July 31st |
![]() |
Saturday, July 30th East Side of S.R. 224 |